Planning | Form: (02 ) 400428084 9/25/2013 | Maximize equipment and wellhead setbacks from occupied buildings and residences to the extent feasible and practicable, as determined by Encana. |
Community Outreach and Notification | Form: (02 ) 400428084 9/25/2013 | Prior to commencement of any new drilling or completion operations, provide to an Erie designated staff member the following for the well-site for informational purposes only, which Encana may revise from time to time during operations:
a) A summary of planned operations, including identified access points and operational timeline, for posting to a local community information web-page
b) A site plan for site preparation, mobilization and demobilization
c) A plan for interim reclamation and vegetation of the site and final reclamation of the site
d) A plan for noise, light and dust mitigation, to the extent feasible
e) A traffic management plan
f) Updates of this information if any change during operations
|
Community Outreach and Notification | Form: (02 ) 400428084 9/25/2013 | Prior to commencement of any new drilling or completion operations, provide notification to landowners within one-half (1/2) mile of the well-site. |
Drilling/Completion Operations | Form: (02 ) 400428084 9/25/2013 | Utilize steel-rim berms around tanks and separators instead of sand or soil berms |
Drilling/Completion Operations | Form: (02 ) 400428084 9/25/2013 | Utilize a high-low pressure vessel (HLP) and vapor recovery unit (VRU) for new wells drilled. Encana may remove the VRU system at such time Encana determines that the VRU system is no longer necessary due to reduced emission recoveries and/or efficiencies, but no earlier than one (1) year after the new well is drilled |
Drilling/Completion Operations | Form: (02 ) 400428084 9/25/2013 | Prior to drilling operations, Operator will perform an anti-collision scan of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision scan will include definitive MWD or gyro surveys of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed well path with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well will only be drilled if the anti-collision scan results indicate that there is not a risk for collision, or harm to people or the environment. For the proposed well, upon conclusion of drilling operations, an as-constructed gyro survey will be submitted to COGCC with the Form 5.
|
Drilling/Completion Operations | Form: (02 ) 400428084 9/25/2013 | Encana will comply with the “COGCC Policy for Bradenhead Monitoring During Hydraulic Fracturing Treatments in the Greater Wattenberg Area”, dated May 29, 2012. |
Drilling/Completion Operations | Form: (02 ) 400428084 9/25/2013 | Utilize closed-loop systems for drilling and completion operations to minimize the need for earthen pits |
Community Outreach and Notification | Form: (02 ) 400868161 11/16/2015 | Planning Prior to commencement of any new drilling or completion operations, provide to an
Erie designated staff member the following for the well-site for informational purposes
only, which Encana may revise from time to time during operations:
a) A summary of planned operations, including identified access points and operational
timeline, for posting to a local community information web-page
b) A site plan for site preparation, mobilization and demobilization
c) A plan for interim reclamation and vegetation of the site and final reclamation of the
site
d) A plan for noise, light and dust mitigation, to the extent feasible
e) A traffic management plan
f) Updates of this information if any change during operations |
Community Outreach and Notification | Form: (02 ) 400868161 11/16/2015 | Prior to commencement of any new drilling or completion operations, provide
notification to landowners within one-half (1/2) mile of the well-site. |
Construction | Form: (02 ) 400868161 11/16/2015 | Maximize equipment and wellhead setbacks from occupied buildings and residences
to the extent feasible and practicable, as determined by Encana. |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | Utilize closed-loop systems for drilling and completion operations to minimize the need
for earthen pits |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | Utilize steel-rim berms around tanks and separators instead of sand or soil berms |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | Prior to drilling operations, Operator will perform an anti-collision scan of existing offset
wells that have the potential of being within close proximity of the proposed well. This
anti-collision scan will include definitive MWD or gyro surveys of the offset wells with
included error of uncertainty per survey instrument, and compared against the
proposed well path with its respective error of uncertainty. If current surveys do not
exist for the offset wells, Operator may have gyro surveys conducted to verify
bottomhole location. The proposed well will only be drilled if the anti-collision scan
results indicate that there is not a risk for collision, or harm to people or the
environment. For the proposed well, upon conclusion of drilling operations, an asconstructed
gyro survey will be submitted to COGCC with the Form 5. |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | Encana will comply with the “COGCC Policy for Bradenhead Monitoring During
Hydraulic Fracturing Treatments in the Greater Wattenberg Area”, dated May 29,
2012. |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | Utilize a high-low pressure vessel (HLP) and vapor recovery unit (VRU) for new wells
drilled. Encana may remove the VRU system at such time Encana determines that the
VRU system is no longer necessary due to reduced emission recoveries and/or
efficiencies, but no earlier than one (1) year after the new well is drilled |
Drilling/Completion Operations | Form: (02 ) 400868161 11/16/2015 | One of the first wells drilled on the pad will be logged with Cased-hole Pulsed Neutron
Log with Gamma Ray Log from TD into the surface casing. All wells on the pad will
have a cement bond log with gamma-ray run on production casing (or on intermediate
casing if production liner is run) into the surface casing. The horizontal portion of every
well will be logged with a measured-while-drilling gamma-ray log. The Form 5,
Completion Report, for each well on the pad will list all logs run in that well and have
those logs attached. The Form 5 for each well shall clearly state “No open-hole logs
were run” and shall reference the Rule 317.p Exception granted for the well. |