Engineer | Form: (02 ) 400429240 6/27/2013 | 1) Provide 48 hour notice prior to spud via electronic Form 42.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Reclamation Specialist | Form: (04 ) 401018168 4/22/2016 | Approval/passing of the form 4 acknowledges that the Oil and Gas Conservation
Commission has received the Notice. It is not an acknowledgement that the reclamation
has been passed. A field inspection will be conducted at a future date to evaluate
compliance with reclamation standards. |
Public Room | Form: (04 ) 401018168 4/22/2016 | Enough topsoil will be saved and stockpiled to cover final reclamation of the location. |
Reclamation Specialist | Form: (04 ) 401018168 4/22/2016 | Mechanical treatment will be used for weed management until desirable perennial
vegetation has become established. At that point weed management through the use of
chemical treatments may be incorporated. |
Reclamation Specialist | Form: (04 ) 401018168 4/22/2016 | Unless operator has (and can provide) evidence of reclamation success through the use
of Cornstalk as a mulch type, straw mulch shall be used. |