| Engineer | Form: (02) 400361040 01/15/2013 | 1)Provide notice of MIRU via an electronic Form 42.
2)Comply with Rule 317.i and provide cement coverage to a minimum of 200' above the Niobrara. Verify cement coverage with a cement bond log per 317.o.
|
| Permit | Form: (02) 400361040 01/16/2013 | Operator must meet Water Well Testing requirements as per amended Rule 318Ae(4)
|
| Permit | Form: (04) 400569717 03/25/2014 | Operator shall comply with Buffer Zone Move-In, Rig-Up Notice Policy dated 12-16-2013. |
| Permit | Form: (04) 400569717 03/25/2014 | Open hole resistivity and gamma logs shall be run to describe the stratigraphy of the entire wellbore and to adequately verify the setting depth of surface casing and aquifer coverage. On a multi-well pad, these open hole logs are only required on one of the first wells drilled on the pad and the Drilling Completion Report - Form 5 for every well on the pad shall identify which well was logged. |
| Permit | Form: (04) 400569717 03/25/2014 | Operator must comply with COGCC Policy for Bradenhead Monitoring During Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012. |
| Engineer | Form: (04) 400569717 04/18/2014 | Operator acknowledges the proximity of the listed non-operated wells. Operator agrees to provide mitigation Option 1 or 2 (per the DJ Basin Horizontal Offset Policy), ensure all applicable documentation is submitted, and submit Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API Number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Kissler-Amen et al 1-25 (API 123-11462)
Monfort 34-25 (API 123-11680) |
| Engineer | Form: (04) 400569717 04/18/2014 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well. |