Engineer | Form: (02 ) 400377256 2/19/2013 | 1) Provide 48 hour notice of spud via electronic Form 42.
2) Set at least 900’ of surface casing. Cement to surface.
3) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
4) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (04 ) 402962503 3/9/2022 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
|