| Permit | Form: (02) 400297534 06/29/2012 | Operator must comply with COGCC Policy for Bradenhead Monitoring During Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.
|
| Permit | Form: (02) 400297534 06/29/2012 | Operator must meet Water Well Testing requirements as per amended Rule 318Ae(4)
|
| Permit | Form: (02) 400297534 06/29/2012 | Operator shall run an open hole log across the surface casing shoe on the first well drilled from this pad.
|
| Engineer | Form: (02) 400297534 06/29/2012 | 1)Provide notice of MIRU via an electronic Form 42.
2)Comply with Rule 317.i and provide cement coverage from the end of the production casing to a minimum of 200' above the Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with a cement bond log.
|
| Engineer | Form: (04) 404304037 08/04/2025 | Operator shall continue to monitor pressure and report to ECMC through annual testing. If monitored well conditions meet reaction threshold or indicate a deficiency, a new bradenhead test and sundry must be filed. |