| Permit | Form: (02) 400253262 03/16/2012 | Operator must meet Water Well Testing requirements as per amended Rule 318A.
|
| Engineer | Form: (02) 400253262 04/04/2012 | 1)Provide 48 hour notice of MIRU via an electronic Form 42.
2)Comply with Rule 317.i and provide cement coverage from the end of the production casing to a minimum of 200' above the Niobrara. Verify coverage with a cement bond log.
3)Comply with Rule 321. Run and submit Directional Survey from TD to surface. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
4)At least two weeks prior to spud notice, the centralizer and cementing plans shall be submitted to the COGCC for review on a Form 4, Sundry Notice.
5)At least one well on the pad must have a complete set of open hole logs (Compensated Neutron, Dual Induction, Resistivity, etc.) run from TD to surface and submitted to the COGCC.
6)Four hours prior to running any casing, notification shall be provided to Ryan Hollinshead, COGCC Engineer at 303-894-2100 x5134.
7)Circulation prior to cementing shall be done to accepted industry standards.
8)A cement ticket documenting the cementing of the production casing shall be submitted in addition to the need for the CBL.
9)Bradenhead pressures shall be taken 6, 12, 24 and 48 hours after cementing production casing and prior to stimulation of the well. Once stimulation is complete, the bradenhead pressure shall be recorded at 24 hours, at 48 hours and at one week post-stimulation. Bradenhead pressures greater than 100 psi must be immediately reported on a Form 17 to the COGCC, sent to the attention of Ryan Hollinshead.
10)This well shall have a bradenhead test preformed on an annual basis.
11)All bradenhead pressures shall be monitored with a gauge that has a maximum reading of one thousand pounds per square inch (psi).
|
| Engineer | Form: (06) 401369566 08/25/2017 | 1) Prior to starting plugging operations a Bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineering for sampling requirements. The Form 17 shall be submitted within 10 days of the test.
|
| Engineer | Form: (06) 401369566 08/25/2017 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For the 581’ plug: pump plug and displace. If surface casing plug is not circulated to surface then tag plug – must be at 431’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ of cement in the casing for each plug.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
|