| Permit | Form: (02) 400241646 02/01/2012 | Operator must meet water well sampling requirements as per Rule 318A. |
| Engineer | Form: (02) 400241646 02/13/2012 | 1) Provide 24 hour notice of MIRU to John Montoya by e-mail at John.Montoya@state.co.us. Indicate Spud Notice in the subject line and provide the following information: Operator Name, Well Name and Number, API #, Spud Date, Contact Name, Contact Phone #, Email Address.
2) Provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) If dry hole, set 40 sks cement 50’ above Niobrara top, 50 sks cement from 50’ below to 50’ above surface casing shoe, 15 sks cement top of surface casing, cut 4’ below GL, weld on plate, 5 sks cement in rat hole & 5 sks cement in mouse hole.
4) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| OGLA | Form: (06) 402690541 06/07/2021 | 1. Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment.
2. This oil and gas location is within a CPW-mapped Pronghorn Winter Concentration Area high priority habitat (HPH). Plugging and abandonment (P&A) activities should not occur from January 1 to April 30. If site conditions warrant that P&A activities must occur from January 1 to April 30, Operator will consult with CPW to develop measures to avoid, minimize, and mitigate adverse impacts to wildlife. |
| Engineer | Form: (06) 402690541 06/08/2021 | In accordance with the Notice to Operators (NTO): Timing for COGCC Forms adopted on 05/01/2020, this Form 6 Notice of Intent to Abandon is valid for 12 months from the date of approval expiring on 6/8/2020. This NTO does not alter the deadlines for submission of, or compliance with any other Commission rule or Form. |
| Engineer | Form: (06) 402690541 06/08/2021 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
| Engineer | Form: (06) 402690541 06/08/2021 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) After placing the plug at 3150', operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the 1600’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 425’ or shallower and provide 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug.
6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
|
| Well File Verification | Form: (04) 402573433 07/15/2021 | This approval is good for one year and a new application must be made before 3/17/2022. Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 402936499 04/14/2022 | Effective Apr 30, 2022 this well will be designated inactive and must be properly returned to production, plugged, have an approved 5B or added to a Form 6A list no later than November 1, 2022.
|