| Engineer | Form: (02) 400222647 11/30/2011 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us .
2) Provide cement coverage from base of intermediate casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (04) 402045258 04/12/2022 | For combustion of gas due to upset conditions, criteria set forth by 903.d.(1) limiting the duration and requiring records being kept of those instances where combustion was necessary must be followed after January 15, 2021. |