| Permit | Form: (02) 400194199 10/24/2011 | Operator must meet water well testing requirements per Rule 318A.
|
| Engineer | Form: (02) 400194199 11/04/2011 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Shannon to 200’ above Sussex. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (04) 401353111 03/23/2018 | This approval is good for one year and a new application must be made before July 25, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application. A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
| Engineer | Form: (04) 401706899 10/26/2018 | This approval is good for one year and a new application must be made before July 24, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 401706899 11/05/2018 | This approval is good for one year and a new application must be made before July 18, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (06) 401993708 05/16/2019 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 401993708 05/16/2019 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
|
| Engineer | Form: (06) 401993708 05/16/2019 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines per Rule 1105. File electronic Form 42 once abandonment of on-location flowlines complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
3) Plug added for J-sand isolation.
4) Need to verify cement at surface casing shoe with CBL, if there is not cement from 50' below to 50' above the surface casing shoe a squeeze (or cutting and pulling casing deeper) will be needed. Submit CBL with Form 6 Subsequent Report of Abandonment. |
| Engineer | Form: (04) 402113002 12/26/2019 | This approval is good for one year and a new application must be made before July 18, 2020. Updates for the planned utilization of the well should be included with the application.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. |
| Engineer | Form: (04) 402447595 07/08/2021 | This approval is good for one year and a new application must be made before July 18, 2021. Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 402767108 04/29/2022 | Effective April 30, 2022 this well will be designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or added to a Form 6A list no later than November 1, 2022. |