| Engineer | Form: (02) 400179735 07/21/2011 | 1)Note surface casing setting depth change from 500’ to 750’. Increase cement coverage accordingly and cement to surface.
2)Provide 24 hour notice of MIRU to Bo Brown via e-mail at bo.brown@state.co.us.
3)Comply with Rule 317.i and provide cement coverage from the end of the production casing to a minimum of 200' above the Niobrara. Verify coverage with cement bond log.
4)Comply with Rule 321. Run and submit Directional Survey from the end of production casing to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|