| Engineer | Form: (02) 400174348 07/18/2011 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Comply with Rule 317.i and provide cement coverage from end of 7" production casing to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (04) 402263889 12/23/2019 | A new application must be made before August 8, 2020. Updates for the planned utilization of the well should be included with the application.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. |
| Engineer | Form: (04) 402658716 04/27/2022 | Effective April 30, 2022 this well will be designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or added to a Form 6A list no later than November 1, 2022. |