Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-33548FRITZLER
6-6-17
PDC ENERGY INC
69175
PA
1/10/2023
WATTENBERG
90750
WELD  123
SESE 17 6N66W 6
319142View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
400130299
02/18/2011
1) Provide 24 hour notice of MIRU to Ed Binkley at 970-506-9834 or e-mail at ed.binkley@state.co.us 2) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
EngineerForm: (04)
401843188
01/06/2020
This approval is good for one year and a new application must be made before June 18, 2020. Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04)
401843188
01/06/2020
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04)
402403245
06/04/2020
This approval is good for one year and a new application must be made before May 20, 2021. Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04)
402403245
06/04/2020
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04)
402688748
05/18/2021
This approval is good for one year and a new application must be made before May 13, 2022. Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04)
402688748
05/18/2021
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (06)
403114167
08/03/2022
Prior to starting plugging operations a Bradenhead test shall be performed if there has not been a reported Bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
EngineerForm: (06)
403114167
08/03/2022
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06)
403114167
08/03/2022
For Wells with known Bradenhead pressures: 1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide 48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via electronic Form 42. These are 2 separate notifications, required by Rules 408.e and 408.I. 2) After placing the shallowest hydrocarbon isolating plug (1510'), operator must wait a sufficient time to confirm static conditions. 3) After placing plug at 1510’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. 4) Prior to placing the 888’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 5) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 638’ or shallower and provide at least 10 sx plug at the surface. 6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
EngineerForm: (06)
403114167
08/03/2022
FLOWLINE AND SITE CLOSURE Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a COGCC Spill/Release Report, Form 19, associated with the abandoned line.
OGLAForm: (06)
403114167
08/05/2022
Due to proximity to a surface water, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the surface water.
OGLAForm: (06)
403114167
08/05/2022
Due to close proximity to Residential Building Units: prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the PA operations.
 
COGIS - Best Management Practice Results
No records to display.