Engineer | Form: (02 ) 400098457 11/26/2010 | 1) Note surface casing setting depth change from 800’ to 980’. Increase cement coverage accordingly and cement to surface.
2) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at jim.precup@state.co.us.
3) If completed, provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
4) If dry hole, set 60 sks cement from 50’ below D Sand base to 100’ above D Sand top, 40 sks cement 50’ above Niobrara top, 50 sks cement ½ out, ½ in surface casing, 10 sks cement top of surface casing, cut 4’ below GL, weld on plate, 5 sks cement in rat hole & 5 sks cement in mouse hole. Restore surface location.
|
Permit | Form: (06 ) 403402595 5/18/2023 | Submit Operator's Monthly Production Reports (Form 7) required for compliance with Rule 413 within 30 days. Missing Jsand 3/2012-7/2012.
|
OGLA | Form: (06 ) 403402595 6/7/2023 | Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date. |
OGLA | Form: (06 ) 403402595 6/7/2023 | Prior to commencing operations, the operator will post signs in conspicuous locations at intersections that will remain in place throughout the duration of the plug and abandonment activities. The signs will indicate plugging and abandonment operations are being conducted, the well name, well, and the applicable contact information. Signs will be placed so as not to create a potential traffic hazard. |
OGLA | Form: (06 ) 403402595 6/7/2023 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to the proximity of residential building units (RBUs) all blowdown gasses will be controlled. |
OGLA | Form: (06 ) 403402595 6/7/2023 | Due to proximity of plugging and abandonment (P&A) operations to BUs, operator will comply with Table 423 Maximum Permissible Noise Levels for residential land use. Prior to initiating work, operator will install temporary sound walls, straw bales, or other BMPs to dampen noise if necessary for compliance. |
OGLA | Form: (06 ) 403402595 6/7/2023 | 3rd party wildlife surveys will be conducted on this well prior to rigging up for P&A activities. Should sensitive HPH conditions be identified during the screening process, Chevron will delay the work until conditions (nesting) clear and/or consult directly with CPW for guidance and discussion of potential mitigation measures that may be incorporated. |
Engineer | Form: (06 ) 403402595 6/8/2023 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
Engineer | Form: (06 ) 403402595 6/8/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Prior to placing cement above the base of the Upper Pierre (approximately 1930’) : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) Pump surface casing shoe plug only after isolation has been verified. Circulate cement to surface if production casing is not pulled.
4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
Engineer | Form: (06 ) 403402595 6/8/2023 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a COGCC Spill/Release Report, Form 19, associated with the abandoned line.
|