| Engineer | Form: (02) 400098307 11/09/2010 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (06) 400365353 01/14/2013 | 1) Provide 48-hour notice of MIRU to Jim Precup at (303) 726-3822.
2) Provide an “As Plugged” wellbore diagram identifying the specific plugging completed.
3) For the surface casing shoe plug, if not circulated to surface, tag plug, it must be at least 696’ or higher, and a surface plug must be provided.
4) If unable to pull casing, contact COGCC for plugging modifications.
5) Properly abandon any flowlines as per Rule 1103.
|
| Inspector | Form: (04) 400476216 02/26/2014 | Location must comply with COGCC Rule 1004 for Final Reclamation and pass a Final Reclamation Inspection. |