Engineer | Form: (02 ) 2590345 10/1/2010 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (06 ) 401952245 3/12/2019 | Plugging
• Provide 48 hour notice of plugging MIRU via electronic Form 42.
• Plugs and squeezes will be placed as stated in the Plugging Procedure section of the approved NOIA unless revised by COA or prior approval from COGCC is obtained.
• Due to the history of bradenhead pressure on this well, operator must wait 8 hrs after pumping the 2500-2304’ plug and assure there is no fluid migration or shut-in pressure on the well. Contact COGCC Engineer for revised plugging orders if well is not static at this time prior to continuing with plugging operations.
• Tag 2500-2304’ plug if circulation is not maintained while pumping and displacing plug to depth, 100’ minimum required.
• Triple Combo of 3/31/12 on file with the COGCC is a partial log. Submit full log from TD to surface casing with Form 6 SRA.
• Check for fluid migration or shut-in pressure on the well prior to pumping any plug(open hole, annular or casing) that isolates deepest aquifer or the surface casing shoe (whichever is deeper). Contact COGCC Area Engineer for revised plugging orders if well is not static at this time prior to continuing with plugging operations.
• Tag required if the shoe plug, or combined stub/shoe plug, is not circulated to the surface. Shoe plug shall be placed as specified herein and the top of cement must be a minimum 50’ into the shoe, or 50’ above the stub (if not cut below the shoe), whichever is shallower.
• Place a 50' plug (minimum) at the surface, both inside the inner most casing and in all annular spaces. All other cement plugs, without mechanical isolation, shall have at least 100' of cement left in the casing. Confirm cement to surface in all strings during cut and cap.
• Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
• Document COAs have been met on the Form 6 SRA.
|
Engineer | Form: (06 ) 401952245 3/12/2019 | Bradenhead Testing
• Prior to the start of plugging operations, a bradenhead test shall be performed and reported if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
• If any of the following conditions exist then sampling of all fluids is required and sampling methods shall comply with Operator Guidance – Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling as found on the COGCC website, cogcc.state.co.us.
1) The initial pressure measurement on the bradenhead is greater than 25 psi, prior to blowing down any liquid or gas from the bradenhead valve, or
2) Pressure remains at the conclusion of the test, or
3) Any liquids are present anytime during the test. If so, then stop the test as soon as liquids are present and sample before resuming the test.
• Form 17 Bradenhead Test Report shall be submitted within 10 days of the test.
• If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples. Submit via a Form 43 to upload the laboratory results to the COGCC Environmental Database. Form 43 instructions are on COGCC’s website under Regulation => Forms => Form 43 COGCC Environmental Database.
|
Engineer | Form: (06 ) 401952245 3/12/2019 | Venting
Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
|
Engineer | Form: (04 ) 402289955 2/18/2020 | 1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead mitigation, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples.
3. During the first day of mitigation operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. During the shut-in period record pressure data to adequately characterize the build-up. This mitigation plan may be used for six consecutive months.
4. At the conclusion of the six months, conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans and the flow rate information and pressure data.
|
Engineer | Form: (04 ) 402476097 9/21/2020 | Operator shall continue to monitor pressure, and report to COGCC through annual test reporting.
|
Engineer | Form: (04 ) 402600867 2/18/2021 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead mitigation, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples.
3. Operator will implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. During the shut-in period record pressure data to adequately characterize the build-up. This mitigation plan may be used for six consecutive months from the date test reported on the Form 17.
4. At the conclusion of the six months (06/21/2021), conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, and the flow rate information and pressure data. |
Engineer | Form: (04 ) 402600867 2/18/2021 | Shut in bradenhead pressure shall not exceed 50 psig. |
Engineer | Form: (04 ) 402770350 8/20/2021 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Shut in bradenhead pressure shall not exceed 50 psig. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
3. Within thirty days of 08/04/2022, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data.
4. Shut well in for at least seven days to monitor build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test.
5. If a sample has not been collected from surface casing within the last twelve months collect bradenhead gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples. |
Engineer | Form: (04 ) 403156434 9/12/2022 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Shut in bradenhead pressure shall not exceed 50 psig. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
3. Within thirty days of 09/06/2023, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data.
4. Shut well in for at least seven days to monitor and collect data to characterize build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test.
5. If a sample has not been collected from surface casing within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples. |
Engineer | Form: (04 ) 403518629 9/11/2023 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
|
OGLA | Form: (06 ) 403843590 7/22/2024 | Due to proximity to a wetland, surface water and expected shallow groundwater, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water. |
Engineer | Form: (06 ) 403843590 7/23/2024 | Prior to starting plugging operations a Bradenhead test shall be performed if there has not been a reported Bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples. |
Engineer | Form: (06 ) 403843590 7/23/2024 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 403843590 7/23/2024 | For Wells with known Bradenhead pressures:
1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide 48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via electronic Form 42. These are 2 separate notifications, required by Rules 408.e and 408.I.
2) After placing the shallowest hydrocarbon isolating plug (3100'), operator must wait a sufficient time to confirm static conditions.
3) After placing plug at 3100’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact ECMC engineering before continuing operations.
4) Prior to placing the 1021’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders.
5) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 858’ or shallower and provide at least 10 sx plug at the surface.
6) After surface plug and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed. |
Engineer | Form: (06 ) 403843590 7/23/2024 | FLOWLINE AND SITE CLOSURE
1) Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
2) Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line. |