Engineer | Form: (04 ) 401371681 10/17/2017 | 1) Prior to starting repair work a bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present sampling is required before pumping any cement. The Form 17 shall be submitted within 10 days of the test.
2) After completing repair work a Bradenhead Test shall be performed within the next 60 days and the Form 17 submitted within 10 days of the test.
3) The additional cement referenced shall be placed as indicated. The placed cement shall be verified with a CBL and documented with a Form 5. Submit a Completed Interval Report, Form 5A, within 30 days after a formation is temporarily abandoned. |