| Engineer | Form: (04) 404006983 01/15/2025 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead mitigation, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the ECMC within three months of collecting the samples.
3. Operator will implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. During the shut-in period record pressure data to adequately characterize the build-up. This mitigation plan may be used for six consecutive months from the date test reported on the Form 17.
4. At the conclusion of the six months 5/25/25, conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, and the flow rate information and pressure data.
Shut in bradenhead pressure shall not exceed 50 psig.
|
| Engineer | Form: (04) 404209502 06/02/2025 | Operator will perform a Mechanical Integrity Test and file an updated pressure management plan sundry no later than 7/1/25. |
| Engineer | Form: (04) 404314128 08/27/2025 | The well must be repaired and successfully pass a MIT or plugged and abandoned within 6 months of failed test date, no later than 1/8/2026.
|
| Engineer | Form: (04) 404314128 08/27/2025 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to the specified abatement system. Shut in bradenhead pressure shall not exceed threshold pressure. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
3. With the Form 6S include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data.
|
| OGLA | Form: (06) 404393178 10/21/2025 | Location is in a CPW mapped Mule Deer Severe Winter Range High Priority Habitat. Although plugging and abandonment operations with heavy equipment will be allowed, the Operator is strongly encouraged to avoid them between December 1 through April 30. |
| OGLA | Form: (06) 404393178 10/21/2025 | Operator committed to the following Best Management Practices under the Technical Detail/ Comments section on the Submit Tab:
3rd party wildlife surveys will be conducted on this well prior to rigging up for P&A activities.
Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date. |
| OGLA | Form: (06) 404393178 10/21/2025 | Due to proximity to a wetland and surface water, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water. |
| Engineer | Form: (06) 404393178 11/06/2025 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) After placing plug at 2273’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact ECMC engineering before continuing operations.
3) Prior to placing cement above the base of the Upper Pierre (1300') : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders.
4) Pump surface casing shoe plug only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 371’ or shallower and provide a minimum of 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
6) After surface plug and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
| Engineer | Form: (06) 404393178 11/06/2025 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include details with the Form 27. |
| Engineer | Form: (06) 404393178 11/06/2025 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
| Engineer | Form: (06) 404393178 11/06/2025 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
If there is a need for sampling, contact ECMC engineering for verification of plugging procedure. |