Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-26094MATRIX
14-29
EXTRACTION OIL & GAS INC
10459
PA
9/28/2023
WATTENBERG
90750
WELD  123
SESW 29 6N65W 6
333308View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04 )
403014807
5/4/2022
1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Prior to starting Bradenhead mitigation, if a sample has not been collected within the last twelve months collect Bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples. 3. During the first day of mitigation operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the Bradenhead. During the shut-in period record pressure data to adequately characterize the build-up. This mitigation plan may be used for six consecutive months. 4. At the conclusion of the six months, conduct a new Bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans and the flow rate information and pressure data.
EngineerForm: (04 )
403014807
5/4/2022
Shut in Bradenhead pressure shall not exceed 50 psig.
OGLAForm: (06 )
403321373
5/23/2023
Prior to commencing operations, the operator will post signs in conspicuous locations at intersections that will remain in place throughout the duration of the plug and abandonment activities. The signs will indicate plugging and abandonment operations are being conducted, the well name, well, and the applicable contact information. Signs will be placed so as not to create a potential traffic hazard.
OGLAForm: (06 )
403321373
5/23/2023
Due to close proximity to Building Units (BUs) and Residential Building Units (RBUs): prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the P&A operations.
OGLAForm: (06 )
403321373
5/23/2023
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to the proximity of BUs and RBUs all blowdown gasses will be controlled.
OGLAForm: (06 )
403321373
5/23/2023
Due to proximity of plugging and abandonment (P&A) operations to Building Units (BUs) and Residential Building Units (RBUs), operator will comply with Table 423 Maximum Permissible Noise Levels for residential land use. Prior to initiating work, operator will install temporary sound walls, straw bales, or other BMPs to dampen noise if necessary for compliance.
EngineerForm: (06 )
403321373
5/26/2023
Revised the TOC for the First string from 180’, to 370', to agree with the CBL in the well file.
EngineerForm: (06 )
403321373
5/26/2023
Prior to starting plugging operations a Bradenhead test shall be performed if there has not been a reported Bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
EngineerForm: (06 )
403321373
5/26/2023
For Wells with known Bradenhead pressures: 1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide 48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via electronic Form 42. These are 2 separate notifications, required by Rules 408.e and 408.I. 2) After placing the shallowest hydrocarbon isolating plug (1240'), operator must wait a sufficient time to confirm static conditions. 3) After placing plug at 1240’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. 4) Prior to placing the 684’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 5) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 559’ or shallower and provide at least 10 sx plug at the surface. 6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
EngineerForm: (06 )
403321373
5/26/2023
FLOWLINE AND SITE CLOSURE 1) Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. 2) Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a COGCC Spill/Release Report, Form 19, associated with the abandoned line.
 
COGIS - Best Management Practice Results
No records to display.