COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06 )
402060496
6/3/2019
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06 )
402060496
6/3/2019
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) Prior to placing the 751' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 501' or shallower and provide 10 sack plug at surface. 4) Leave at least 100’ of cement in the wellbore for each plug. 5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
EngineerForm: (06 )
402060496
6/3/2019
If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required, and the COGCC engineering staff must be contacted. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. 3) If sampling is required contact COGCC engineering for a confirmation of plugging requirements prior to placing any plugs. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (04 )
402000112
2/4/2020
This approval is good for one year and a new application must be made before April 9, 2020. Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04 )
402000112
2/4/2020
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04 )
402000112
2/4/2020
Please update production reporting from March, 2019 through June, 2019 to reflect TA status and not SI.
EngineerForm: (04 )
402000112
2/4/2020
This well was plugged, June, 2019, waiting on the Subsequent Form 6.
 
COGIS - Best Management Practice Results
No records to display.