| Engineer | Form: (04) 402308158 09/09/2021 | 1) This approval is good for one year and a new application must be made 1 year from prior application. Updates for the planned utilization of the well should be included with the application.
2) Perform a bradenhead test and submit a Form 17 prior to submittal of the next year’s request for continued TA status.
3) A Form 5A, Completed Interval Report, is required to report all plugs currently downhole which isolate any perforated interval.
4) The Form 7, Operators Report of Monthly Operations, must correctly reflect the well status and dates reported on the Form 4, Sundry Notice-Request for Continued Temporarily Abandoned Status.
|
| Engineer | Form: (04) 402308158 09/09/2021 | Emailed operator for economic evaluation. Price as of Sep-2021 is economic. Evaluating line pressure. Subsequent TA application must provide the price environment if a satellite compressor is necessary.
|