| Permit | Form: (06) 401015836 04/21/2016 | Production records need to be corrected prior to the approval of the Subsequent Report of Abandonment (Form 6). (J Sand reports Sep 2014 thru present) |
| Engineer | Form: (06) 401015836 04/22/2016 | 1) Prior to starting plugging operations, a bradenhead test shall be performed. Call COGCC with the results of the test before plugging for sampling requirements. The Form 17 shall be submitted with Form 6 (s) Subsequent of Abandonment.
2) Provide 48 hour notice of plugging MIRU via electronic Form 42.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
4) Please submit gyro survey data with Form 6 (s) Subsequent Report of Abandonment.
5) Stub plug is also shoe plug, this plug must be tagged at 578’ or shallower. Leave at least 100’ cement in the casing for each plug.
|