| Engineer | Form: (06) 401586972 05/17/2018 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 401586972 05/17/2018 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon all flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
3) Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
4) Please submit gyro survey data with Form 6 Subsequent Report of Abandonment.
5) Tag CIBP at 7400’ to confirm there, dump two sacks of cement on CIBP. If CIBP is not tagged where expected contact COGCC Engineer to update plugging orders. Production casing stub plug is also surface casing shoe plug, this plug must be tagged at 820’ or shallower. Leave at least 100’ of cement in the wellbore for each plug. |
| Engineer | Form: (06) 402200021 10/08/2019 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
| Engineer | Form: (06) 402200021 10/08/2019 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 970' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 820' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) After placing the shallowest hydrocarbon isolating plug (4135'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. |
| Engineer | Form: (06) 402200021 10/08/2019 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required, and the COGCC engineering staff must be contacted.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
3) If sampling is required contact COGCC engineering for a confirmation of plugging
requirements prior to placing any plugs.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions.
The Form 17 shall be submitted within 10 days of the test. |
| Engineer | Form: (06) 402200021 10/08/2019 | Tag CIBP at 7400’ to confirm there, dump two sacks of cement on CIBP. If CIBP is not tagged where expected contact COGCC Engineer to update plugging orders. |
| Engineer | Form: (04) 402307597 08/14/2020 | 1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead mitigation, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples.
3. Operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. During the shut-in period record pressure data to adequately characterize the build-up.
4. This mitigation plan may be used until October 1, 2020, then conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry no later than October 31, 2020, that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, and the flow rate information and pressure data.
|
| Engineer | Form: (04) 402567798 01/11/2021 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to be plugged no later than 12/31/2021. Pressure is to be managed and mitigated until plugging is complete. Summary of well monitoring and mitigation will be submitted on a Form 4 Sundry within 30 days of the well being plugged and abandoned but no later than 12/31/2021. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description.
3. Shut in bradenhead pressure shall not exceed 50 psig. |
| Engineer | Form: (06) 402589209 02/05/2021 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 402589209 02/05/2021 | 1) Provide 42 business day notice of plugging MIRU via electronic Form 42.
2) After placing the shallowest hydrocarbon isolating plug (4135'), operator must wait a sufficient time to confirm static conditions.
3) After placing squeeze at 2000’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
4) Prior to placing the 975’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
5) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 820’ or shallower and provide at least 10 sx plug at the surface.
6) Leave at least 100’ of cement in the wellbore for each plug.
7) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 90 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
8) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed. |
| Engineer | Form: (06) 402589209 02/05/2021 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
| OGLA | Form: (06) 402947496 02/04/2022 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. |
| Engineer | Form: (06) 402947496 02/10/2022 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
| Engineer | Form: (04) 402940726 02/11/2022 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to plugged no later than 12/31/2022. Pressure is to be managed and mitigated until plugging is complete. Summary of well monitoring and mitigation will be submitted on a Form 4 Sundry within 30 days of the well being plugged and abandoned but no later than 12/31/2022. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description.
3. Shut in bradenhead pressure shall not exceed 50 psig.
|
| Engineer | Form: (06) 402947496 02/14/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) After placing the shallowest hydrocarbon isolating plug (4325'), operator must wait a sufficient time to confirm static conditions.
3) After placing plug at 1900’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
4) Prior to placing the 970’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
5) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 820’ or shallower and provide at least 10 sx plug at the surface.
6) Leave at least 100’ of cement in the wellbore for each plug.
7) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
8) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed. |