| Engineer | Form: (04) 402351147 04/20/2020 | This approval is good for one year and a new application must be made before March 25, 2021. Updates for the planned utilization of the well should be included with the application.
|
| Engineer | Form: (04) 402351147 04/20/2020 | The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402351147 04/20/2020 | Please update production reporting from January, 2019 present to reflect TA status and not SI.
|
| Engineer | Form: (04) 402618066 08/03/2021 | 1) This approval is good for one year and a new application must be made before 5/17/2022. Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (06) 402818370 10/04/2021 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| OGLA | Form: (06) 402818370 10/04/2021 | Operator will implement measures to control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare, and the environment. |
| Engineer | Form: (06) 402818370 10/04/2021 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) After placing the shallowest hydrocarbon isolating plug (6457'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the 725’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 475’ or shallower and provide 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug.
6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
| OGLA | Form: (06) 402818370 10/04/2021 | Operator will review stormwater controls to prevent impacted stormwater and sediment from entering surface waters. |
| Engineer | Form: (06) 402818370 10/04/2021 | In accordance with the Notice to Operators (NTO): Timing for COGCC Forms adopted on 05/01/2020, this Form 6 Notice of Intent to Abandon is valid for 12 months from the date of approval expiring on 10/4/2022. This NTO does not alter the deadlines for submission of, or compliance with any other Commission rule or Form. |