Engineer | Form: (06 ) 401357882 10/17/2017 | If this well is not plugged prior to 2/19/2018.
Prior to initiation of plugging operations, a Bradenhead test shall be performed. If there is 25# or greater present at the beginning of the test call COGCC Engineer for possible sampling requirements. Form 17 shall be submitted within 10 days. |
Engineer | Form: (06 ) 401357882 10/17/2017 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 1675’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 840’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ of cement in the casing for each plug.
4) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment is complete.
|