WELL05-123-17932ENDSLEY
32-1J5
KERR MCGEE OIL & GAS ONSHORE LP
47120
PA
8/23/2022
WATTENBERG
90750
WELD  123
NENE 32 3N65W 6
336352View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
400690578
09/24/2014
1) The additional cement referenced shall be placed as indicated and comply with Rule 317.i. The placed cement shall be verified with a CBL and documented with a Form 5 Drilling Completion Report. 2) Please submit gyro survey data with Form 5 Drilling Completion Report.
EngineerForm: (04)
402307172
08/14/2020
1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Prior to starting bradenhead mitigation, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples. 3. Operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. During the shut-in period record pressure data to adequately characterize the build-up. 4. This mitigation plan may be used until October 1, 2020, then conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry no later than October 31, 2020, that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, and the flow rate information and pressure data.
EngineerForm: (04)
402569538
01/19/2021
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Well to be plugged no later than 12/31/2021. Pressure is to be managed and mitigated until plugging is complete. Summary of well monitoring and mitigation will be submitted on a Form 4 Sundry within 30 days of the well being plugged and abandoned but no later than 12/31/2021. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description. 3. Shut in bradenhead pressure shall not exceed 50 psig.
EngineerForm: (04)
402940643
02/11/2022
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Well to plugged no later than 12/31/2022. Pressure is to be managed and mitigated until plugging is complete. Summary of well monitoring and mitigation will be submitted on a Form 4 Sundry within 30 days of the well being plugged and abandoned but no later than 12/31/2022. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description. 3. Shut in bradenhead pressure shall not exceed 50 psig.
OGLAForm: (06)
403056117
06/07/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to proximity of building units (BUs) all blowdown gases will be controlled.
OGLAForm: (06)
403056117
06/07/2022
Prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the PA operations.
EngineerForm: (06)
403056117
06/15/2022
Prior to starting plugging operations a Bradenhead test shall be performed if there has not been a reported Bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
EngineerForm: (06)
403056117
06/15/2022
1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide 48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via electronic Form 42. These are 2 separate notifications, required by Rules 408.e and 408.I. 2) After placing the shallowest hydrocarbon isolating plug (1190'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. 3) Prior to placing the 1095’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 941’ or shallower and provide 10 sx plug at the surface. 5) Leave at least 100’ of cement in the wellbore for each plug. 6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines. 7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
 
COGIS - Best Management Practice Results
No records to display.