| Engineer | Form: (04) 401270609 05/01/2017 | 1) Prior to starting repair work a bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineer for sampling requirements before pumping any cement. The Form 17 shall be submitted within 10 days of the test.
2) The additional cement referenced shall be placed as indicated. The placed cement shall be verified with a CBL and documented with a Form 5. Submit gyro survey data with the Form 5. |