| Engineer | Form: (06) 400746820 12/12/2014 | Note changes to plugging procedure:
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For 1250’ plug: pump plug and displace. If surface casing plug is not circulated to surface then tag plug – must be 321’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ cement in the casing for each plug.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
|
| Permit | Form: (06) 400816455 06/13/2016 | Submit form 7 showing PA for 4/2015 and 5/2015. |