Permit | Form: (02 ) 2286085 11/28/2011 | Operator must meet water well testing requirements per Rule 318A.
|
Engineer | Form: (06 ) 401107991 10/13/2016 | 1) Prior to starting plugging operations, a bradenhead test shall be performed. If any pressure remains at the conclusion of the test or any liquids were present contact COGCC Engineer for sampling requirements. The Form 17 shall be submitted within 10 days of the test.
2) Provide 48 hour notice of plugging MIRU via electronic Form 42.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
4) Tag CIBP at 7490' and dump 2 sacks of cement on top. Production casing stub plug is also surface casing shoe plug, this plug must be tagged at 617’ or shallower. Leave at least 100’ cement in the wellbore for each plug. |