Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-14298STATE LEASE 81
14-16
PDC ENERGY INC
69175
PA
3/2/2017
WATTENBERG
90750
WELD  123
SWSW 16 6N64W 6
327196View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (06)
401197587
01/31/2017
Please submit 5A reporting the Ft. Hays as well as updated form 7 reporting for the Ft. Hays. Do this before the form 6 subsequent is approved.
EngineerForm: (06)
401197587
02/06/2017
1) Prior to starting plugging operations a bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, contact COGCC Engineer for sampling requirements. If pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineer for sampling requirements. The Form 17 shall be submitted within 10 days of the test. 2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU. 3) Properly abandon flowlines. Once flowlines are properly abandoned, file electronic form 42. 4) For 1150’ plug: pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours and tag plug – top of plug must be not deeper than 275’ and provide minimum 10 sx plug at the surface. Leave at least 100’ of cement in the wellbore for each plug.
 
COGIS - Best Management Practice Results
No records to display.