Permit | Form: (06 ) 402347653 3/23/2020 | Reported "as drilled" GPS data is suspect. Submit accurate "as drilled" GPS data on Subsequent Report of Abandonment. GPS data must meet the requirements of Rule 215. |
Engineer | Form: (06 ) 402347653 3/25/2020 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
Engineer | Form: (06 ) 402347653 3/25/2020 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
|
Engineer | Form: (06 ) 402347653 3/25/2020 | 1) Provide 48-hour notice of plugging MIRU via electronic Form 42.
2) After placing the shallowest hydrocarbon isolating plug (4450'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) The plug at 4350' needs to be placed and have an 8-hour WOC to assure that all fluid migration has been stopped. If that doesn’t isolate the flow, additional attempts in front of the 1567' plug will need to be attempted. Other downhole potential squeeze opportunities may need to be looked at before the 1567’ plug.
4) Prior to placing the 1567’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
5) When pumping surface casing plug (503'), if cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 253’ or shallower and provide 10 sx plug at the surface.
6)Leave at least 100’ of cement in the wellbore for each plug.
7) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
8) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
|