COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06)
401226866
03/08/2017
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) For the 1500’ plug: pump plug and displace. If surface casing plug is not circulated to surface then tag plug – must be at 248’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ of cement in the casing for each plug. 3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete. 4) Prior to starting plugging operations a Bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineering for sampling requirements. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (06)
401514017
02/05/2018
Prior to starting plugging operations a Bradenhead test shall be performed. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. 3) If sampling is required contact COGCC engineering for an confirmation of plugging requirements prior to placing any plugs. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (06)
401514017
02/05/2018
Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06)
401514017
02/05/2018
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) Prior to placing the 400’ plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 248’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ of cement in the casing for each plug. 4) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment is complete.
 
COGIS - Best Management Practice Results
No records to display.