Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-13065SOONER UNIT
2-28
FOUNDATION ENERGY MANAGEMENT LLC
10112
PA
4/2/2019
SOONER
77700
WELD  123
NWNE 28 8N58W 6
323461View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06)
401889999
02/11/2019
Plugging: 1) Provide 48 hour notice of MIRU via electronic Form 42. 2) Submit Plug verification for CIBP and cement at 6240'. 3) Shoe plug: Tag plug 50’ above surface casing shoe. 4) Surface plug: Cement from 50' to surface in casing and annulus. Bradenhead: 1) If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations a Bradenhead test shall be performed. The Form 17 shall be submitted within 10 days of the test. 2) If before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 3) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Venting during plugging: Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. Flowlines: Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
 
COGIS - Best Management Practice Results
No records to display.