Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-12805ARISTOCRAT
31-10C
CRESTONE PEAK RESOURCES OPERATING LLC
10633
PA
10/19/2023
ARISTOCRAT
2925
WELD  123
NWNE 10 3N65W 6
311345View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (06 )
403378039
6/27/2023
Due to proximity to surface water, Operator will review the stormwater program and implement stormwater BMPs and erosion control measures as needed to prevent fine-grained sediment and impacted stormwater runoff from entering surface water.
OGLAForm: (06 )
403378039
6/27/2023
This oil and gas location is within 0.5-mile of a CPW-mapped bald eagle nest area. Plugging and abandonment (P&A) should not occur from December 1 to July 31. If site conditions warrant that P&A activities must be performed from December 1 to July 31, Operator will consult with the regional CPW Energy Liaison to develop site specific measures to avoid, minimize, or mitigate impacts to wildlife.
OGLAForm: (06 )
403378039
6/27/2023
This oil and gas location is within a CPW-mapped bald eagle roost or communal roost Rule 309.e.(1) consultation habitat. CPW may choose to consult on this planned P&A to develop site specific measures to avoid, minimize, and mitigate impacts to wildlife prior to conducting the work. Please note that non-emergency plugging and abandonment (PA) activities should not take place from November 15 to March 15. Please confirm via email if a consultation with CPW has or will occur and provide any operator BMPs that are the result of that consultation.
PermitForm: (06 )
403378039
7/31/2023
Correct Sussex production reporting. Sussex was abandoned on 2/15/04, however Form 7s are reporting PR/SI/TA status from March 2004-July 2016. Make a request to our production team to delete the incorrect reports and then submit new Form 7s with "AB" status for two months following the abandonment.
EngineerForm: (06 )
403378039
8/1/2023
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples. If there is a need for sampling, contact ECMC engineering for verification of plugging procedure.
EngineerForm: (06 )
403378039
8/1/2023
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Prior to placing cement above the base of the Upper Pierre (approximately 1524’) : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 3) Pump surface casing shoe plug only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 382’ or shallower and provide a minimum of 10 sx plug at the surface. 4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06 )
403378039
8/1/2023
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
 
COGIS - Best Management Practice Results
No records to display.