| OGLA | Form: (06) 403079686 07/18/2022 | Prior to commencing operations, the operator will post a sign or signs in conspicuous locations. The signs will indicate the approximate dates that the plugging and abandonment operations are being conducted, the well names, and the applicable contact information. Signs will be placed so as not to create a potential traffic hazard. |
| OGLA | Form: (06) 403079686 07/18/2022 | Prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the PA operations. |
| Engineer | Form: (06) 403079686 07/18/2022 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 403079686 07/18/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) After placing the shallowest hydrocarbon isolating plug (4225'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the 825’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 675’ or shallower and provide 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug.
6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
| Engineer | Form: (06) 403079686 07/18/2022 | Verify existing cement coverage by CBL - submit to COGCC for verification of plugging orders prior to continuing plugging operations. |