| Agency | Form: (02) 2582224 05/18/2010 | 1) Provide cement bond log to verify isolation of Shannon and Sussex
2) If this work has not been performed, then provide remedial cement coverage from 200’ below Shannon to 200’ above Sussex (minimum coverage 5140’ to 4145’). Verify remedial coverage with cement bond log.
3) Submit wellbore diagram with annotations. (WBDs received – static diagram with well table and WBD with depths and cement tops – no casing dimensions – need well table details incorporated into WBD) |
| Engineer | Form: (04) 400520294 12/02/2013 | The additional cement referenced shall be placed as indicated and comply with Rule 317.i. The placed cement shall be verified with a CBL and documented with a Form 5. |
| Engineer | Form: (06) 401483099 01/11/2018 | Prior to starting plugging operations a bradenhead test shall be performed.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples. |
| Engineer | Form: (06) 401483099 01/11/2018 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon all flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
3) Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
4) Please submit gyro survey data with Form 6 Subsequent Report of Abandonment.
5) Leave at least 100’ of cement in the wellbore for each plug. |