| Permit | Form: (06) 401676492 06/18/2018 | Requirement for compliance with Rule 309: Operator’s Monthly Report of Operations, Form 7. Form 7 reporting shall be corrected for the J Sand. The months that require correction are dependent on the tagging of the CIBP placed 12/1/2004. If CIBP is tagged, the Form 7 reporting should be TA from 12/2004 to current. If CIBP is not tagged, correction of the production reporting from 2/2015 to current is required. Submittal of a Form 7 in correction of these deficiencies is required for compliance with Rule 309 within 30 days. |
| Engineer | Form: (06) 401676492 06/20/2018 | Tag plug at 7665' set on 12/01/2004. Dump bail 2 sacks cement on plug. If plug is not there, contact COGCC engineering staff for further plugging orders |
| Engineer | Form: (06) 401676492 06/20/2018 | Operator shall implement measures to control unnecessary and excessive venting, to
protect the health and safety of the public, and to ensure that vapors and odors from
well plugging operations do not constitute a nuisance or hazard to public welfare. |
| Engineer | Form: (06) 401676492 06/20/2018 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 729’ plug: verify that all fluid migration (liquid or gas) has been
eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer
for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated
to surface, shut-in, WOC 4 hours then tag plug – must be at 479’ or shallower and
provide 10 sx plug at the surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once
abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
|
| Engineer | Form: (06) 401676492 06/20/2018 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
3) If sampling is required contact COGCC engineering for an confirmation of plugging
requirements prior to placing any plugs.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions.
The Form 17 shall be submitted within 10 days of the test.
|