| Agency | Form: (02) 1758982 09/25/2009 | <style type="text/css">
p {margin:0px 0px 0px 2px;}
ul {margin-top:2px;margin-bottom:2px;}
ol {margin-top:2px;margin-bottom:2px;}
H1 {font-family:Arial;font-size:28px;text-align:Left;vertical-align:Middle;color:#000000;font-weight:bold;}
H2 {font-family:Arial;font-size:24px;text-align:Left;vertical-align:Middle;color:#000000;font-weight:bold;}
H3 {font-family:Arial;font-size:18px;text-align:Left;vertical-align:Middle;color:#000000;font-weight:bold;}
.Normal {font-family:Arial;font-size:14px;text-align:Left;vertical-align:Middle;color:#000000;}
.TableDefault {border-collapse:collapse;border:1px solid #000000;}
.TableDefault th {padding:2px;vertical-align:top;text-align:left;border:1px solid #000000;}
.TableDefault td {padding:2px;vertical-align:top;text-align:left;border:1px solid #000000;}
</style>
<p><span class="Normal">Prior to recomplete, operator must: 1) Verify existing cement above the Niobrara, Sussex and across the Fox </span><span class="Normal">Hills Aquifer with a cement bond log. 2) If it is not present as follows, provide remedial cement 200’ above </span><span class="Normal">Niobrara (minimum cement top of 7200’), 200’ below Sussex to 200’ above Sussex (minimum coverage 4500’ </span><span class="Normal">to 5000), and 800 into the surface casing shoe. Verify remedial cement coverage with cement bond log. </span></p>
|
| Engineer | Form: (02) 1634968 04/25/2011 | Prior to recomplete, operator must: 1) Verify existing cement above the Niobrara, Sussex and across the Fox Hills
Aquifer with a cement bond log.
2) If it is not present as follows, provide remedial cement 200’ above Niobrara (minimum cement top of 7200’), 200’ below Sussex to 200’ above Sussex (minimum coverage 4500’ to 5000), and 800 into the surface casing shoe. Verify remedial cement coverage with cement bond log. |
| Engineer | Form: (04) 400616809 05/29/2014 | The additional cement referenced shall be placed as indicated and comply with Rule 317.i. The placed cement shall be verified with a CBL and documented with a Form 5 Drilling Completion Report. |
| Engineer | Form: (06) 400657025 08/14/2014 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) Please tag existing CIBP w/2 sxs @ 7369'. If satisfactory contractor wireline reports confirming setting of CIBP w/ 2sxs @ 7369' emailed to COGCC prior to plugging operations beginning no need to tag.
3) For 900' plug: pump plug and displace, shut-in, WOC 4 hours and tag plug – must be 156’ or shallower.
4) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
5) Please submit available documentation showing 8/10/2004 setting of CIBP w/ 2 sxs @ 7950' and contractor reports showing 6/4/2014 setting of CIBP w/ 2 sxs @ 7369' with form 6 (s).
|