COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (02)
402988840
10/05/2022
Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
EngineerForm: (02)
402988840
10/31/2022
1)Operator shall comply with the most current revision of the Northwest Colorado Notification Policy. See attached notice. 2)Operator shall provide cement coverage from the production casing shoe (4+1/2" SECOND STRING) to a minimum of 200' above all Mesa Verde Group (and Ohio Creek Formation, if present) oil, gas, and water-bearing sandstone and coalbed formations. Verify production casing cement coverage with cement bond log.
EngineerForm: (04)
404108194
03/03/2025
1) For applicable operations, report work completed within 30 days on a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not an updated WBD in the well file submit an updated WBD. 2) For applicable operations, submit a Form 5 or 5A (updated packer and tubing depths) within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run. 3) Complete casing pressure test and include documentation in subsequent repair form 4) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations 5) Operator shall notify ECMC Engineering staff of changes and/or additional repair methods to the approved repair procedure.
EngineerForm: (04)
404108194
03/03/2025
Complete repair work or P&A well within 6 months of identifying the integrity issue
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
402988840
11/9/2022
Alternative Logging Program: One of the first wells drilled on this pad will be logged with an open-hole resistivity log with gamma-ray, from TD into the 9 5/8” casing shoe. All wells on the pad will have a cement bond log (CBL) with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The Form 5, Completion Report, for each well on the pad will list all logs run and have those logs attached. The Form 5 for a well without open-hole logs will state “Alternative Logging Program - No open-hole logs were run” and will clearly identify the type of log and the well (by API#) in which open-hole logs were run.