| Construction | Form: (02 ) 401972082 9/16/2020 | -A Field Wide Stormwater Management Plan (SWMP) for the Piceance Creek Program is on file at the XTO Energy Inc.(21459 CR5, Rifle, CO, 81650) office. A Site Specific SWMP including a Site Plan is in place for this location.
-Spill Prevention, Control and Countermeasures (SPCC) for the Piceance Creek Program is on file at the XTO Energy Inc. (21459 CR5, Rifle, CO, 81650) office. The Field Wide and Site Specific SWMPs each address SPCC during construction operations.
-Inspections of the project site and maintenance of installed BMP’s shall be conducted in accordance with the CDPHE CDPS permit and field wide plan. |
| Drilling/Completion Operations | Form: (02 ) 401972082 9/16/2020 | Open-hole Resistivity Log with Gamma Ray Log will be run from the kick-off point into the surface casing. A Cement Bond Log with Gamma-Ray will be run on production casing, or on intermediate casing if a production liner is run. The horizontal portion of the wellbore will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, will list all logs run and have those logs attached. |