COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (02)
401422060
12/26/2017
Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
OGLAForm: (02)
401422060
01/05/2018
The moisture content of water/bentonite based mud (WBM) generated drill cuttings managed onsite shall be kept as low as practicable to prevent accumulation of liquids greater than de minimis amounts. The operator has indicated in the ‘DRILLING WASTE MANAGEMENT PROGRAM SECTION’ of the Form 2; that ‘Cuttings Disposal’ will be “OFFSITE” and that the ‘Cuttings Disposal Method’ will be “Beneficial reuse”, ‘Other Disposal Description’ as “PLEASE SEE WASTE MANAGEMENT PLAN ATTACHED TO ASSOCIATED FORM 2A.” Any proposed offsite disposal or beneficial reuse of cuttings to another oil and gas location shall not occur until approval of a Form 4 Sundry Notice specifying disposal or beneficial reuse location and cuttings material sampling and characterization methods. A Form 4 Sundry Notice must also be submitted for any of the WBM drill cuttings that will remain on the well pad location and must be sampled and meet the applicable standards of Table 910-1.
EngineerForm: (02)
401422060
01/08/2018
1)Operator shall comply with the most current revision of the Northwest Colorado Notification Policy. 2)Operator shall provide cement coverage from the production casing shoe (4+1/2" FIRST STRING) to above total vertical depth of 4100’. Isolation is required due to offset Wasatch sand injection. Verify production casing cement coverage with a cement bond log.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
401422060
1/27/2018
One of the first wells that Ursa Operating Company drills on the pad will be logged with open-hole Resistivity Log and Gamma Ray Log from TD into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The Form 5, Completion Report, for each well on the pad will list all logs run and have those logs attached. The Form 5 for a well without open-hole logs shall clearly state “No open-hole logs were run” and shall clearly identify (by API#, well name & number) the well in which open hole logs were run.