Storm Water/Erosion Control | Form: (02 ) 400238148 3/30/2012 | STORM WATER PLANS AND EROSION CONTROL METHODS WILL BE USED TO INSURE SITE STABILIZATION AND TO INSURE ADEQUATE ENVIRONMENTAL SAFEGUARDS ARE IN PLACE TO PREVENT ANY STORM WATER RUNOFF. INSPECTIONS WILL BE DOCUMENTED AND FILED IN THE RANGELY FIELD OFFICE. CHEVRON RANGELY HAS A ANNUALLY REVIEWED FIELD WIDE STORMWATER MANAGEMENT PLAN. |
General Housekeeping | Form: (02 ) 400238148 3/30/2012 | THE WELL SITE WILL BE MAINTAINED IN A SANITARY CONDITION AT ALL TIMES AND ALL WASTE MATERIALS SHALL BE DISPOSED OF PROMPTLY AT APPROPRIATE WASTE DISPOSAL SITES. |
Material Handling and Spill Prevention | Form: (02 ) 400238148 3/30/2012 | ALL FLUIDS WILL STORED IN APPROPRIATE CONTAINERS AND IN SECONDARY CONTAINMENT SYSTEMS ENGINEERED TO CONTAIN 150 PERCENT OF THE LARGEST VESSEL VOLUME. CHEVRON HAS ANNUALLY UPDATED ENGINEER CERTIFIED FULL FIELD SPCC PLAN IN ACCORDANCE WTH THE FEDERAL REQUIREMENTS OF 40 CFR PART 112. |
Wildlife | Form: (02 ) 400238148 3/30/2012 | POWERLINE DESIGN TO MINIMIZE RAPTOR ELECTROCUTION RISK, NO NEW SURFACE WORK FROM APRIL 15- TO JULY 15 TO ALLOW FOR PRAIRIE DOG REPRODUCTIVE PERIOD. |
Construction | Form: (02 ) 400238148 3/30/2012 | CHEVRON WILL EMPLOY DUST SUPPRESSION TECHNIQUES OF FRESHWATER. USING EXISTING LEASE ROADS TO MINIMIZE SURFACE DISTRUBANCE. TWO FLOWLINES WILL RUN IN A COMMON TRENCH TO A CENTRALIZED COLLECTION STATION, AND WILL FOLLOW EXISTING PIPELINE RIGHT OF WAYS. ALL ROADS WILL BE CROWNED AND DITCHED ACCORDING TO BLM MANUAL SECTION 9113. |