OGLA | Form: (04 ) 403119666 8/3/2022 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well completion(s), well repair/maintenance, well perforating, temporary abandonment activities, additional equipment installation, and/or testing operations with a workover rig, wireline rig, or other heavy equipment do not constitute a nuisance or hazard to public health, welfare and the environment. |
Engineer | Form: (04 ) 403119666 8/18/2022 | 1) Report work completed with a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes submit an updated WBD.
2) If wellbore geometry changes or cement work is executed, submit information on a Form 5 in lieu of a Form 4 Sundry
3) Complete a bradenhead test following completion of the repair and submit results on a Form 17 or directive approved method
|