| Engineer | Form: (04) 403194237 11/16/2022 | 1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report
2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method.
3) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan
4) Submit a current WBD on a Form 4 Sundry “COMPLIANCE with CONDITION OF APPROVAL (COA)” by 02/31/23
5) Complete installation of BH monitoring system by 3/31/2023 |