Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-103-10865PICEANCE CREEK UNIT
297-11A3
QB ENERGY OPERATING LLC
10844
SI
1/1/2026
PICEANCE CREEK
68800
RIO BLANCO  103
NESE 11 2S97W 6
335946View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
AgencyForm: (02)
1890055
05/29/2009
24 HOUR SPUD NOTICE REQUIRED. E-MAIL: DAVID.ANDREWS@STATE.CO.US CEMENT TOP VERIFICATION BY CBL REQUIRED. THE MOISTURE CONTENT OF ANY DRILL CUTTINGS IN A CUTTINGS PIT, TRENCH, OR PILE SHALL BE AS LOW AS PRACTICABLE TO PREVENT ACCUMULATION OF LIQUIDS GREATER THAN DE MINIMIS AMOUNTS. AT THE TIME OF CLOSURE, THE DRILL CUTTINGS MUST ALSO MEET THE APPLICABLE STANDARDS OF TABLE 910-1. NO PORTION OF ANY PIT THAT WILL BE USED TO HOLD LIQUIDS SHALL BE CONSTRUCTED ON FILL MATERIAL, UNLESS THE PIT AND FILL SLOPE ARE DESIGNED AND CERTIFIED BY A PROFESSIONAL ENGINEER, SUBJECT TO REVIEW AND APPROVAL BY THE DIRECTOR PRIOR TO CONSTRUCTION OF THE PIT. THE CONSTRUCTION AND LINING OF THE PIT SHALL BE SUPERVISED BY A PROFESSIONAL ENGINEER OR THEIR AGENT. THE ENTIRE BASE OF THE PIT MUST BE IN CUT. THE PROPOSED SURFACE CASING IS MORE THAN 50' BELOW THE DEPTH OF THE DEEPEST WATER WELL WITHIN 1MILE OF THE SURFACE LOCATION WHEN CORRECTED FOR ELEVATION DIFFERENCES. THE DEEPEST WATER WELL WITHIN 1 MILE IS 0 FEET DEEP. THE OPERATOR SHALL COMPLY WITH RULE 321. AND IT SHALL BE THE OPERATOR'S RESPONSIBILITY TO ENSURE THAT THE WELLBORE COMPLIES WITH SETBACK REQUIREMENTS IN COMMISSION ORDERS OR RULES PRIOR TO PRODUCING THE WELL.
EngineerForm: (04)
403233324
11/23/2022
1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report 2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method. 3) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan -Include diagnostic information on causal factors for intermediate casing pressure. 4) Complete installation of BH monitoring system by 3/31/2023
EngineerForm: (04)
404413921
02/25/2026
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. No later than 6/12/26, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, flow rate information and SCADA pressure data. 3. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
 
COGIS - Best Management Practice Results
No records to display.