Engineer | Form: (04 ) 403024751 4/27/2022 | 1. This sundry to conduct bradenhead diagnostic evaluations is valid until 10/22/2022 (6 months from bradenhead test date)
2. For Wells that have sustained casing pressure above the action threshold, flows liquids or continuous gas from the bradenhead annulus as determined through diagnostic testing and evaluation, the Operator will provide a PMP with the Form 4, including a description of the Operator’s findings from the previous 6 months, number of times the well was blown down, a current WBD and future plans for more frequent monitoring or testing, pressure mitigation, or remedial well work by 10/22/2022
3. Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges. |
Engineer | Form: (04 ) 403618362 12/11/2023 | 1)Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report or other Director approved submittal method.
2)Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges.
3)Any liquids blown down are to be collected, stored, handled, and treated or disposed as E&P waste per COGCC’s 900 series rules.
4)At least one check valve is required for annular spaces that are tied to sales line or separator. Maintain equipment for pressure regulation and check valves in good working order.
5)At least one valve is required to monitor pressure and sample flow from the bradenhead.
6)Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan
7)Complete installation of bradenhead system by 06/30/2024 |