Engineer | Form: (04 ) 403181483 11/15/2022 | 1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report
2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method.
7) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan -Include diagnostic information on causal factors for intermediate casing pressure.
5) Complete installation of BH monitoring system by 3/31/2023
4) Perform diagnostics on BH and Intermediate pressures being the same and report results on Sundry required by COA#3 |