Engineer | Form: (04 ) 401521521 3/22/2018 | This approval is good for one year and a new application must be made before January 22, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
Engineer | Form: (04 ) 401192135 3/22/2018 | This approval is good for one year and a new application must be made before January 24, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
Engineer | Form: (04 ) 401736043 8/17/2018 | This approval is good for one year and a new application must be made before January 22, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
Engineer | Form: (04 ) 401881235 2/27/2019 | This approval is good for one year and a new application must be made before 1 year from prior application. Updates for the planned utilization of the well should be included with the application. |
Engineer | Form: (04 ) 402269618 3/26/2020 | 1) This approval is good for one year and a new application must be made before 1/9/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 402551561 4/19/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
Engineer | Form: (04 ) 402905122 1/27/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Please update status of all applicable months from SI to TA for 1/1999 forward (production reporting digital records do not go back to 1996)
3) Submit a Wellbore Diagram on a Form 4 Sundry
|