Engineer | Form: (04 ) 400422963 5/23/2013 | 1) Run new CBL across squeeze to verify remedial cement coverage. 2) Within 30 days after the work is complete, submit Form 5 showing new cement configuration, remedial squeeze cement tickets, new CBL, and historic CBL (run on 5/22/1980, showing the original, reported TOC of 3600’). |
Engineer | Form: (04 ) 400436012 6/27/2013 | Within 30 days after the work is complete, submit Form 5 showing new remedial cement (7" csg) and second string (new 5-1/2" csg) configuration, remedial squeeze cement tickets (7" csg), primary cement (5-1/2" csg), new CBL (7" csg - required as a Condition of Approval on COGCC Document No. 400422963), and historic CBL (run on 5/22/1980, showing the original, reported 7" csg TOC of 3600’). |