| Engineer | Form: (04) 401514262 03/22/2018 | This approval is good for one year and a new application must be made before January 16, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
| Engineer | Form: (04) 401186793 03/22/2018 | This approval is good for one year and a new application must be made before January 17, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
| Engineer | Form: (04) 401722266 08/06/2018 | This approval is good for one year and a new application must be made before January 16, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
| Engineer | Form: (04) 401871803 04/18/2019 | This approval is good for one year and a new application must be made before January 16, 2020(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
|
| Engineer | Form: (04) 402269658 03/30/2020 | 1) This approval is good for one year and a new application must be made before 1/09/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
| Engineer | Form: (04) 402562356 01/13/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402910100 02/08/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) Submit a current Wellbore Diagram on a Form 4 Sundry
|