Engineer | Form: (04 ) 401514227 3/21/2018 | This approval is good for one year and a new application must be made before January 16, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
Engineer | Form: (04 ) 402505661 10/26/2020 | 1) This approval is good for one year and a new application must be made before 10/07/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 402551765 1/21/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
Engineer | Form: (04 ) 402794547 10/6/2021 | 1) This sundry to conduct bradenhead diagnostic evaluations is valid until 2/27/2022
2) For Wells that have sustained casing pressure above the action threshold as determined through diagnostic testing and evaluation, the Operator will provide a PMP with the Form 4, including a description of the Operator’s findings from the previous 6 months, number of times the well was blown down, a current WBD and future plans for more frequent monitoring or testing, pressure mitigation, or remedial well work by 2/27/2022
3) Submit the gas sample analysis from previous Form 17 bradenhead test on a Form 43
4) Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges.
|
Engineer | Form: (04 ) 402909427 2/8/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) Submit a current Wellbore Diagram on a Form 4 Sundry |
Engineer | Form: (04 ) 402957599 2/22/2022 | 1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report
2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method.
3) Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges.
4) Any liquids blown down are to be collected, stored, handled, and treated or disposed as E&P waste per COGCC’s 900 series rules.
5) At least one check valve is required for annular spaces that are tied to sales line or separator. Maintain equipment for pressure regulation and check valves in good working order.
6) At least one valve is required to monitor pressure and sample flow from the bradenhead.
7) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan
|